CHI - Power Maintenance
Scheduled Maintenance Report for CloudfloorDNS
Completed
The scheduled maintenance has been completed.
Posted Jul 21, 2021 - 06:42 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 20, 2021 - 16:42 UTC
Scheduled
Reason for Work: UPS3A cutover to new UPS

Risk Mitigation: Best practices and procedures will be followed during this event

Description: Data center operations will be transferring MSB-1 and 2 to generator. They will then transfer UPS 3A and 3B to static bypass. Then all RPPs will be cutover to the new UPS 1A. Once everything has been cut over the UPS will be restored to normal and MSB1 and 2 will be transferred back to utility.
Posted Jun 23, 2021 - 16:45 UTC
This scheduled maintenance affected: DNS.